Decision Dossier report preview

Inside the Stonepine Bridge Upgrade evaluation

Selected extracts from the PDF Decision Dossier, editable comparison workbook and Release Manifest. Every item below relates to the same synthetic project and the same three fictional bidders.

Synthetic demonstration only. No real client, bidder or procurement information is shown.

Deliverables

What the decision team receives

The previews demonstrate the structure and traceability of the evaluation rather than reproducing every page or worksheet.

PDF

Decision Dossier

Executive comparison, detailed findings, evidence references, clarification actions, limitations and decision boundaries.

XLSX

Editable comparison workbook

A working record of the bid comparison, findings register, clarification log and source register.

Manifest

Release Manifest

A controlled record of the deliverables prepared, quality-checked and issued for the project.

Executive overview

The comparative position at a glance

The executive view brings the material differences together without replacing the detailed evidence underneath them.

Bidders compared

3

Bidder A, Bidder B and Bidder C

Submitted prices

$7.66M to $8.92M

Before like-for-like clarification of the identified exclusion

Programme range

11 to 15 months

Bidder B's 11-month programme assumes unconfirmed early access

Selected findings

2 open

Both require clarification before the comparison is concluded

Comparative position

Bidder A and Bidder C are broadly comparable on scope inclusions and commercial basis. Bidder B's lower total is not currently verified on the same basis because structural steel fabrication is excluded, and its programme advantage assumes access earlier than the tender allows. No bidder currently presents a fully qualifying submission without clarification.

This is a synthesis of findings, not a recommendation. AKTE does not select a bidder.

Comparison matrix

Detailed bidder comparison

The matrix brings information from differently structured submissions into a consistent review format.

Stonepine Bridge Upgrade. Exact submitted values are retained; no price normalisation has been applied.
Comparison areaBidder ABidder BBidder CEvidence statusDecision relevanceClarification required
Submitted price$8.14M$7.66M$8.92MClarification requiredBidder B appears lowest, but its total excludes structural steel fabrication.Obtain steel fabrication and installation pricing on the same inclusion basis.
Programme14 months11 months, subject to earlier access15 monthsClarification requiredBidder B's apparent programme advantage depends on access four weeks earlier than the tender allows.Confirm whether early access is available. If not, request a compliant programme.
Structural steel fabricationIncludedExcludedIncludedConfirmedThe submitted totals are not currently comparable on the same scope basis.Resolve through clarification CL-01 before comparative pricing is concluded.
Pricing basisLump sumLump sum with steel excludedLump sumClarification requiredThe description of Bidder B's total as lump sum does not remove the identified scope exclusion.Confirm the full like-for-like total and revised inclusion statement.

Submitted price comparison

Bidder A$8.14M
Bidder B$7.66M
Bidder C$8.92M

Submitted price comparison only. This is not a bidder ranking or award recommendation.

Findings register

Priority findings requiring attention

Detailed findings separate confirmed evidence from unresolved points so the decision team can see what is known and what still requires clarification.

DD-01

Clarification required

Pricing basis differs

Affected bidder: Bidder B

Source: Commercial Submission, p. 18, l. 7; Appendix C, p. 41, l. 10

Observation: Structural steel fabrication is priced separately, and no steel pricing was found in the referenced appendix.

Decision relevance: Bidder B's lower submitted total is not verified on the same scope basis as Bidders A and C.

Clarification action: Request the price to fabricate and install structural steel on the same inclusion basis as Bidders A and C.

DD-02

Clarification required

Programme assumes unconfirmed early access

Affected bidder: Bidder B

Source: Programme Narrative, p. 6, l. 4

Observation: The 11-month programme is conditioned on site access four weeks earlier than the tender date.

Decision relevance: The apparent programme advantage may not be achievable under the issued schedule.

Clarification action: Confirm whether the earlier access date can be provided. If not, request an updated compliant programme.

Evidence trail

From finding to clarification action

Every material finding remains connected to its source so the decision team can verify the basis of the analysis.

1. Finding

DD-01

Pricing basis differs.

2. Source

Commercial Submission

p. 18, l. 7; Appendix C, p. 41, l. 10

3. Observation

Steel excluded

Steel fabrication is separately priced, but no price was found in the referenced appendix.

4. Decision relevance

Totals not comparable

Bidder B's lower total is not yet on the same scope basis.

5. Action

Clarify CL-01

Obtain steel pricing on the same inclusion basis before concluding the comparison.

Clarification register

Questions to resolve before the evaluation is concluded

The register gives the client a practical list of factual points arising from the supported sample findings.

Only questions supported by the existing Stonepine sample are included.
ReferenceBidderRelated findingClarification requiredCurrent statusEffect on comparison
CL-01Bidder BDD-01Provide the price to fabricate and install structural steel on the same inclusion basis as Bidders A and C.OpenSubmitted totals are not yet comparable on a like-for-like scope basis.
CL-02Bidder BDD-02Confirm whether the programme remains achievable using the access date stated in the tender documents.OpenThe stated 11-month programme advantage remains unverified.

Editable workbook

A working record aligned with the PDF dossier

The workbook uses the same bidders, prices, finding IDs, status labels, clarification references and evidence sources as the report.

Workbook views

OverviewBid comparisonFindings registerClarification logSource register
Findings register worksheet preview
Finding IDBidderStatusSourceClarification reference
DD-01Bidder BClarification requiredCommercial Submission, p. 18, l. 7CL-01
DD-02Bidder BClarification requiredProgramme Narrative, p. 6, l. 4CL-02

Release Manifest

A controlled record of the issued deliverables

This simplified preview demonstrates the manifest structure. It contains no fictional signature, approval or delivery date.

Illustrative Release Manifest structure for the Stonepine sample
DeliverableFile typeVersionQuality-check statusRelease status
Decision DossierPDFv1.0Quality-checkedIllustrative sample
Comparison workbookXLSXv1.0Quality-checkedIllustrative sample
Release ManifestPDFv1.0Quality-checkedIllustrative sample

The Release Manifest records the controlled deliverables issued for the project. It does not transfer the client's decision or award authority to AKTE.

Decision authority

Evidence support, not an automated award decision

The Decision Dossier structures the available evidence and highlights matters relevant to the client's evaluation. It does not replace professional judgement, legal or technical advice, bidder clarification, approval governance or the client's award decision.

The client retains responsibility for its evaluation, recommendation, approvals and final procurement decision.

What remains outside this sample

Project and scope overview — the synthetic procurement context, accepted source set, evaluation basis and stated limitations.

Headline bidder comparison — a consistent view of the material information supplied by each synthetic bidder.

Priority findings — issues relevant to the decision, distinguishing facts, conclusions, assumptions and missing information.

Evidence references — the synthetic source document, section and page supporting each material finding.

Clarification actions — questions to resolve where a response is incomplete, ambiguous, inconsistent or materially qualified.

Scope and limitations — what the sample considered, what it did not consider and where professional judgement remains necessary.

The sample is synthetic and does not represent a real client evaluation. It is not a bidder recommendation, legal advice or a guarantee of outcome. Professional judgement and the award decision remain with the client.

Have a tender to compare now?

Begin with the project characteristics and we’ll identify the evaluation route likely to fit.

Begin with a short project fit check. No confidential documents required.

AKTE

Tender Evaluation & Decision Support

We provide independent analytical and decision support. The client remains responsible for the procurement process, applicable legal and regulatory compliance, evaluation rules and final award decision. We do not provide legal advice, certify statutory procurement compliance or automatically select a supplier. © 2026 AKTE. All rights reserved.